Village of Covington, Ohio

  • Community
    • About Covington
    • News & Events
    • History of Covington
      • Introduction of Covington
      • The Mound Builders and American Indians
      • English Settlers and The Revolutionary War
      • The Northwest Territory and Newberry Township
      • First White Settlers
      • Incorporating Covington
      • 1850 to 1900
      • 1900 to 1950
      • 1950 to 2000
      • 2000 to Present
    • Famous People
    • Community Organizations
      • Covington Schools
      • Churches In Covington
      • J. R. Clarke Public Library
      • Covington-Newberry Historical Society
    • Parks & Recreation
    • Highland Cemetery
    • Village Projects
      • High Street Project
      • Schoolhouse Park
      • Wastewater Treatment Plant Project
  • Departments
    • Administration
    • Mayor and Council
      • Council Meeting
      • Village Council Agendas / Minutes
    • Economic Development
      • Covington Development Council (CDC)
      • Community Reinvestment Area (CRA)
      • Downtown Redevelopment District (DRD)
    • Planning and Zoning
      • Planning Commission
      • Board of Zoning Appeals
    • Police Department
    • Public Works Department
    • Utilities Department
    • Tax Department
    • Fire and Rescue
  • Documents
    • Village Council Agendas / Minutes
    • Ordinances and Resolutions
    • Utility Documents
    • Tax Department and Documents
    • Permits & Applications
    • General Village Policies & Procedures
    • Village Fee Schedule
    • Miscellaneous Documents
  • Contact

High Street Project 2.0 UPDATE

October 21, 2021 by Village of Covington

The Village of Covington completed the first phase of the High Street Project earlier this year, which included replacement of utilities within the roadway.  As many people are aware, this project was only the setup for the larger project that was coming in 2022.  Some updates on the High Street Project 2.0 scheduled for 2022!

What is it?

The Ohio Department of Transportation is improving State Route 48 (High Street) from Dodds Street to US36.  The roadway will be reconstructed and widened by one (1) foot on each side (two (2) feet total is being added to the right-of-way) to allow more room for parking and traffic on the roadway.   Additionally, sidewalks and curb ramps are being replaced to improve pedestrian traffic along the roadway.

This project requires that some property owners along High Street will have easements, temporary easements, or other land that will be purchased to be put in the public right-of-way.

More information is available here!

When is this happening?

The planning, funding, and setup work for the project have already begun.  In the coming weeks you will see changes to High Street related to the project!  Some of those changes include:

  • Removal of trees in front of the Government Center to allow the widening of the roadway
  • Movement of utility poles along High Street
  • Utility work related to placement of new poles along High Street

The majority of the road, sidewalk, and other work will be bid out in the Spring of 2022 and completed by the late Fall of 2022.  Once this project is bid out, it will be an ODOT project, but the Village will keep everyone updated as it progresses.

 

 

Filed Under: News & Events

GOVERNMENT CENTER

VILLAGE OF COVINGTON
1 South High Street,
Covington, Ohio 45318
Phone: 937-473-3420
For Emergencies Call 911
Contact Information

NEWS AND EVENTS

  • America 250 Covington Events
  • Garage Sale Day
  • ELECTRIC AND GAS AGGREGATION PROGRAM
  • BOIL ADVISORY IN COVINGTON
  • BID ADVERTISEMENT – COVINGTON – BROADWAY UTILITY

VILLAGE OF COVINGTON

GOVERNMENT CENTER
1 South High Street
Covington, Ohio 45318
Phone: 937-473-3420

POLICE DEPARTMENT
1 South High Street
Covington, Ohio 45318
Emergency Phone: 911
Office Phone: 937-473-2102
Office Fax: 937-473-3853



© Copyright Village of Covington · All Rights Reserved · Developed by Color Green Creative · Hosted by Sozo Technologies · Admin Login