Phase 1 – SPRING 2022
The Schoolhouse Park Master Plan is broken down into multiple phases. Phase 1 (3 acres), which will begin construction in 2022, includes some of the most desired elements for the park, including a splashpad and new restrooms. This phase will be bid out in Spring 2022 and will be completed by 2023.
Work Completed in Phase 1 (Download Phase 1 PDF)
- Demolition and removal of existing conditions
- Earthwork including excavation, grading, adding topsoil, and seeding
- Utilities installation – hydrants, water, sewer, storm, electric
- Pavement / Curb / Sidewalk construction for the Phase 1 area
- Splashpad (30’ x 30’) Construction
- Main Pavilion and Restroom (4,000 square feet) Construction
- *NEW* Amphitheater
Funding for Phase 1:
- Estimated Engineer’s Cost for Phase 1 (not including Amphitheater): $1,048,166.50
- Estimated Engineer’s Cost for Amphitheater: $300,000
- Total Estimated Cost: $1,348,166.50
- LWCF Grant: $500,000 (awarded to Village in March 2022)
- Private Donations for Phase 1: $658,000 (pledged / in hand)
- Public Funding: $325,000 (in 2022 budget)